Which of the following is not a general characteristic of a project?
A) a project has a unique purpose
B) a project has more certainty
C) a project has more uncertainty
D) a project often draws resources from various areas in the organization
Correct Answer:
Verified
Q29: Unlike PERT,CPM incorporates probabilistic time estimates into
Q30: The project management process encompasses
A)planning.
B)scheduling.
C)control.
D)All of these
Q31: Because the critical path is the shortest
Q32: A(n)_ breaks down a project into components,subcomponents,activities,and
Q33: The _ is a document that provides
Q35: With an activity-on-node (AON)network diagram,the nodes indicate
Q36: PERT stands for program enterprise and resource
Q37: A(n)_ is a project team structure that
Q38: The critical path is the longest path
Q39: Indirect costs always increase as a project's
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents