The original difference between CPM and PERT was that
A) CPM was based on the Gantt Chart and PERT wasn't
B) CPM used single activity time estimates while PERT used multiple time estimates
C) CPM used the AOA network convention while PERT used AON
D) there was no difference
Correct Answer:
Verified