With regards to suppliers,lean systems typically require:
A) Delivery of large lots at frequent intervals
B) Buyer inspection of goods and materials
C) Multiple sources from which to purchase
D) Long-term relationships and commitments
E) The lowest price possible
Correct Answer:
Verified