Which of the following statements is NOT true about finite capacity scheduling (FCS) ?
A) FCS is an extension of the Gantt chart reasoning.
B) FCS loads jobs backward from due dates to determine the capacity required at each work center to meet the due dates of each job.
C) FCS assumes that jobs are being scheduled through a number of work centers,each with one or more machines.
D) With the advent of modern computers,FCS has been vastly improved.
E) In FCS,attention is paid to scarce resources to facilitate job flow and to improve the performance of the shop.
Correct Answer:
Verified
Q1: A bottleneck is:
A)A resource that has the
Q3: Which of the following statements is incorrect
Q4: The theory of constraints (TOC)is:
A)A strategic technique
Q6: Theory of constraints,as it applies to business
Q7: Lead time for completion of a job
Q8: The overriding problem in batch scheduling is:
A)Regulating
Q8: Which of the following is NOT primarily
Q11: In the language of constraint management,inventory is:
A)The
Q17: Use a Gantt chart to schedule the
Q25: Throughput is defined as the difference between
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents