Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours, and total flow time for the sequence is 85 hours. For this schedule, utilization is ________ and the average number of jobs in the system is ________.
A) 100 percent; 10.625
B) low; .0941
C) 0.400 or 40 percent; 2.5
D) 0.235 or 23.5 percent; 4.25
E) maximized; minimized
Correct Answer:
Verified
Q60: Three jobs are to be assigned to
Q61: Five jobs are waiting for processing through
Q62: Five welding jobs are waiting to be
Q63: EDD stands for what?
A) earliest due date
B)
Q64: Average completion time for a schedule sequence
Q66: What does the use of the shortest
Q67: Sequencing (or dispatching):
A) assigns dates to specific
Q68: Which of the following dispatching rules ordinarily
Q69: Which of the following dispatching rules tends
Q70: Five jobs are waiting to be processed.
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents