A partially solved PERT problem is detailed in the table below.Times are given in weeks.
a.Calculate the expected time for each activity.Enter these values in the appropriate column in the table above.
b.Which activities form the critical path?
c.What is the estimated time of the critical path?
d.What are the project variance and the project standard deviation?
e.What is the probability of completion of the project after week 40?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q82: The expected activity time in PERT analysis
Q88: Which of the following statements regarding PERT
Q89: The _ distribution is used by PERT
Q91: An activity on a PERT network has
Q92: A project being analyzed by PERT has
Q97: Contract requirements state that a project must
Q98: An activity on a PERT network has
Q100: A local project being analyzed by PERT
Q108: A project whose critical path has an
Q114: Describe in words how to calculate a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents