Dexter Surgical Tools has set the following direct labour standard: 0.5 hours at $20 per hour, for each unit of Tool #11. The company plans to produce 1200 units of Tool #11 in July; however, the actual production was 1000 units and only 900 units were actually sold. The actual labour cost for July was $22 per hour.
Which of the following is a likely explanation for the July labour efficiency variance?
A) The standard was set incorrectly.
B) A machine breakdown has resulted in unanticipated inefficiencies.
C) The production level was smaller than expected.
D) Both incorrectly set standards and a machine breakdown are likely explanations.
Correct Answer:
Verified
Q69: When material price variances are recognised at
Q70: For a particular period a firm worked
Q71: Jasmine Morron is examining a statistical control
Q72: A particular firm with zero material inventory
Q73: In which of the following circumstances would
Q75: A department's budgeted output for a 4-week
Q76: A material price variance of $5000 (unfavourable)
Q77: Which of the following statements is a
Q78: Which of the following statements regarding allowances
Q79: Jay Bole is in the process of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents