Which of the Following Activities Is NOT a Step in the Project

Question 2

Multiple Choice

Which of the following activities is NOT a step in the project monitoring and control phase?


A) Monitoring ongoing project activities
B) Allocating a budget
C) Comparing project variables to the actual plan
D) Identifying corrective actions

Correct Answer:

verifed

Verified