The production planner for Fine Coffees, Inc. produces two coffee blends: American (A) and British (B) . He can only get 300 pounds of Colombian beans per week and 200 pounds of Dominican beans per week. Each pound of American blend coffee requires 12 ounces of Colombian beans and 4 ounces of Dominican beans, while a pound of British blend coffee uses 8 ounces of each type of bean. Profits for the American blend are $2.00 per pound, and profits for the British blend are $1.00 per pound. The goal of Fine Coffees, Inc. is to maximize profits.
What is the objective function?
A) P = A + 2B.
B) P = 12A + 8B.
C) P = 2A + B.
D) P = 8A + 12B.
E) P = 4A + 8B.
Correct Answer:
Verified
Q49: Given the following 2 constraints, which solution
Q50: Which of the following constitutes a simultaneous
Q51: Solving linear programming problems graphically
A) is possible
Q52: Q53: Which of the following could not be Q55: The production planner for Fine Coffees, Inc. Q56: What is the optimal solution for Q57: After the data is collected the next Q58: When using the graphical method, the region Q59:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents