The diagram below shows the activities on the nodes, and the table shows the normal time and crash time (in days) and cost for each activity.
-Which activity should be crashed to reduce the project completion by 2 days?
A) Crash activity B by 1 day and Activity C by 1 day.
B) Crash activity E by 2 days.
C) Crash activity C by 1 day and activity E by 1 day.
D) Crash activity B by 2 days.
Correct Answer:
Verified
Q96: A list of the tasks, broken down
Q97: The critical path is the _ path
Q98: On an AOA diagram, a _ represents
Q99: Consider the following project.
Q100: Consider the following project.
Q102: A PERT/CPM activity has an optimistic time
Q103: Consider the following project.
Q104: Joe used a project management software package
Q105: Consider the following project.
Q106: A PERT/CPM activity has an optimistic time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents