Consider the following project.
-A dummy activity in a PERT network allows us to
A) specify the positive time and resources required to complete the activity.
B) maintain the precedence relationships.
C) add more starting nodes.
D) add more ending nodes.
Correct Answer:
Verified
Q86: The advantage of a Gantt chart over
Q87: On an AOA diagram, a _ represents
Q88: The activities that must be completed prior
Q89: In a CPM/PERT network the critical path
Q90: Project control involves
A) crashing.
B) three time estimates.
C)
Q92: If t is the expected completion time
Q93: A GANTT chart represents mainly
A) an immediate
Q94: Consider the following project.
Q95: Consider the following project.
Q96: A list of the tasks, broken down