The early start of an activity that has more than one predecessor is the minimum of the earliest finishes of all predecessors.
Correct Answer:
Verified
Q33: An AON network will never require dummy
Q34: The early finish for an activity on
Q35: When earliest finish is subtracted from latest
Q36: An AOA network will never require dummy
Q37: Crashing cost is always higher than the
Q39: A work breakdown structure is a useful
Q40: The expected project completion time is assumed
Q41: If the early start for activity A
Q42: The critical path activities have no _.
Q43: Consider the following network.