Johann Builders has a fixed -price contract providing $120,000 of revenue.Construction on the contract was begun in 2013 and was completed in 2014.Information relating to the contract is as follows: What amount of income should Johann recognize in 2014 assuming that the company appropriately uses the percentage-of-completion method of income recognition?
A) $9,286
B) $15,000
C) $17,000
D) $7,000
Correct Answer:
Verified
Q42: On November 30,Monet Company consigned 90 freezers
Q43: The Yoder Supply Company sells maintenance contracts
Q44: In 2014,Charlotte Engineering entered into an agreement
Q45: Hussong,Inc. ,appropriately uses the installment sales method
Q46: On January 3,2014,Continental Services,Inc. ,signed an agreement
Q48: The completed-contract method (as opposed to the
Q49: When a contractor determines that a contract
Q50: Marshland,Inc.had the following consignment transactions during December:
Q51: Warthog Enterprises,which began operations on January 1,appropriately
Q52: Cantor Company sold $400,000 to customers on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents