Question 40

Multiple Choice

Which of the following best describes the critical path of a project?


A) It is the date an entire project should be completed and operational-when the organization can expect to begin to reap the benefits of the project.
B) It identifies the project activities that must be completed,the expected start and end dates,and what resources are assigned to each task.
C) It is a critical date for completing a major part of a project.
D) It consists of all activities that,if delayed,would delay an entire project.

Correct Answer:

verifed

Verified