Which of the following statements about consumption-based planning is TRUE?
A) Planning is based on historical data.
B) Planning is based on exploding the BOM.
C) Dependent demand is derived from independent demand.
D) It is used for high-value materials
E) Planning is based on MPS.
Correct Answer:
Verified
Q52: What does SOP stand for?
A)Sales and operations
Q53: The manner in which CIRs consume PIRs
Q54: In SAP ERP production planning strategy,net requirements
Q55: After the SOP process has generated the
Q56: Which of the following statements best represents
Q58: Exploding the BOM refers to
A)Creating the BOM
Q59: The static lot-sizing procedure
A)Combines the requirements from
Q60: A company would be most likely to
Q61: MRP data are specific to each plant.
Q62: In-house production is the most common procurement
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents