Taft Company produces 5,000 pallets each day.The average number of units in work in process is 10,000,having an average cost of $35,000.The annual carrying costs related to inventory are 20%. Consultants have determined that the work in process could be reduced by as much as 25% by rearranging the factory floor.What would the throughput time be if Harrison implements the recommended changes?
A) Twelve hours
B) One day
C) One and one-half days
D) Two days
Correct Answer:
Verified
Q52: Inventory levels for firms using JIT inventory
Q53: Harrison Industries produces 4,000 lunch boxes each
Q54: Rowe Co.'s Job 401 for the manufacture
Q55: Harrison Industries produces 4,000 lunch boxes each
Q56: Polk,Inc.produces 3,000 hammers each day.The average number
Q58: In a JIT system,reducing throughput time is
Q59: The journal entry to record undamaged direct
Q60: The accounting system used with JIT manufacturing
Q61: The materials account of the Lankford Company
Q62: The materials account of the Herbert Company
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents