A job was budgeted to require 3 hours of labor per unit at $11.00 per hour.The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500.What is the direct labor efficiency variance?
A) $27,500 unfavorable.
B) $22,000 unfavorable.
C) $16,000 unfavorable.
D) $22,000 favorable.
E) $6,000 unfavorable.
Correct Answer:
Verified
Q42: Based on a predicted level of production
Q54: Based on predicted production of 12,000 units,
Q55: A company's flexible budget for 12,000 units
Q77: Based on a predicted level of production
Q78: Georgia,Inc.has collected the following data on one
Q82: Summerlin Company budgeted 4,000 pounds of material
Q83: Hassock Corp.produces woven wall hangings.It takes 2
Q84: Use the following data to find the
Q85: The standard materials cost to produce 1
Q86: A job was budgeted to require 3
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents