A job was budgeted to require 3 hours of labor per unit at $11.00 per hour.The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500.What is the total labor cost variance?
A) $2,000 unfavorable.
B) $3,000 unfavorable.
C) $5,500 unfavorable.
D) $8,000 unfavorable.
E) $9,000 unfavorable.
Correct Answer:
Verified
Q81: A job was budgeted to require 3
Q82: Summerlin Company budgeted 4,000 pounds of material
Q83: Hassock Corp.produces woven wall hangings.It takes 2
Q84: Use the following data to find the
Q85: The standard materials cost to produce 1
Q87: The standard materials cost to produce 1
Q88: Use the following data to find the
Q89: Use the following data to find the
Q90: Use the following data to find the
Q91: The following information describes a company's usage
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents