Manatee Corp. has developed standard costs based on a predicted operating level of 352,000 units of production, which is 80% of capacity. Variable overhead is $281,600 at this level of activity, or $0.80 per unit. Fixed overhead is $440,000. The standard costs per unit are:
Manatee actually produced 330,000 units at 75% of capacity and actual costs for the period were:
Calculate the following variances and indicate whether each variance is favorable or unfavorable:
(1) Direct labor efficiency variance:
$__________________
(2) Direct materials price variance:
$__________________
(3) Controllable overhead variance:
$__________________
Correct Answer:
Verified
Q141: Chips Co. assigned direct labor cost to
Q142: Woods, Inc. budgeted the following overhead costs
Q143: Calais Company's fixed budget for the first
Q144: If Falcon Company's actual overhead incurred during
Q146: Gates Company reports the following information regarding
Q147: The following information comes from the records
Q148: The following information comes from the records
Q149: Gates Company collected the following data regarding
Q150: During November, Heim Company allocated overhead to
Q164: A product has a sales price of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents