In this chart,the letters represent:
A) Activities
B) Milestones
C) Employees
D) Data values
E) Position numbers
Correct Answer:
Verified
Q101: In this chart,note that two arrows point
Q102: The information in PERT charts are commonly
Q103: The latest starting time for activity H
Q104: The slack time for activity D is:
A)2
B)4
C)6
D)9
E)none
Q105: If the project leader now believes that
Q106: In this chart,the circles represent:
A)Activities
B)Milestones
C)Employees
D)Data values
E)References to
Q106: All of these are examples of typical
Q108: The earliest starting time for activity G
Q109: In PERT diagrams the shortest completion time
Q110: Which of the following is the critical