Mya is managing a project.Unfortunately,the entire project team lost four days due to a hurricane in the area and a couple of the project team lost even more time when dealing with insurance claims and rebuilding.At the six-week mark of a nine-week project,she figures the team is one week behind.What might be the BEST solution?
A) Add several people to the project to get it back to schedule
B) Do not change the schedule, but expect the project and development teams to work longer days and every-other weekend.
C) Since the project is about 16% behind, increase the project to about 10-and-one-half weeks
D) Since the project is about 20% behind, increase the project to about 12 week.
E) Add three people to the project - AND - increase the overall project by one week (to a total of ten weeks)
Correct Answer:
Verified
Q24: Micah is a fairly new project manager.He
Q44: PMP is People - Management - Project
Q45: The Throwaway Prototyping methodology is especially good
Q54: _ are created to ensure that team
Q55: PMP is Project Management Professional.
Q55: Investments in information systems projects today are
Q57: CIO is an acronym for "computing information
Q59: Which is probably NOT a standard that
Q60: Rich is a manager in the accounting
Q62: The V-model is a variation of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents