Question 35

Multiple Choice

When using job-order costing, which of the following costs is least likely to be known in a timely manner for decision-making purposes?


A) Direct labor costs
B) Administrative salaries
C) Direct materials costs
D) Manufacturing overhead costs

Correct Answer: