The following data have been recorded for recently completed Job 501 on its job cost sheet. Direct materials cost was $3,067. A total of 30 direct labor-hours and 104 machine-hours were worked on the job. The direct labor wage rate is $12 per labor-hour. The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $11 per machine-hour. The total cost for the job on its job cost sheet would be:
A) $4,571
B) $3,757
C) $3,090
D) $3,427
Correct Answer:
Verified
Q28: In a job-order costing system, direct labor
Q29: Which of the following situations always results
Q30: The Work in Process inventory account of
Q31: Harrell Company uses a predetermined overhead rate
Q32: In a job-order costing system, the amount
Q34: Freeman Company uses a predetermined overhead rate
Q35: In a job-order costing system, the journal
Q36: If a company applies overhead to jobs
Q37: When applying manufacturing overhead to jobs, the
Q38: Which of the following accounts is debited
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents