A Problem with Directly Comparing a Static Planning Budget to Actual

Question 14

True/False

A problem with directly comparing a static planning budget to actual costs is that this comparison fails to distinguish between differences in costs that are due to changes in activity and differences that are due to how well costs were controlled.

Correct Answer: