The calculation of the labor efficiency variance is:


A) Standard hourly rate multiplied by (standard hours minus actual hours) .
B) Standard hours multiplied by (standard rate minus actual rate) .
C) Actual labor hours multiplied by (standard rate minus actual rate) .
D) Actual rate multiplied by (standard hours minus actual hours) .