The calculation of the labor efficiency variance is:
A) Standard hourly rate multiplied by (standard hours minus actual hours) .
B) Standard hours multiplied by (standard rate minus actual rate) .
C) Actual labor hours multiplied by (standard rate minus actual rate) .
D) Actual rate multiplied by (standard hours minus actual hours) .
Correct Answer:
Verified
Q44: The calculation of the labor rate variance
Q47: If the standard quantity of materials is
Q51: Using more direct labor hours for units
Q51: If the standard quantity of materials is
Q54: Controlling the materials quantity variance is usually
Q59: If the hourly wage rate actually paid
Q66: Favorable standard cost variances are normally closed
Q72: The use of inexpensive,low quality,materials often results
Q74: Excessive overtime hours worked by direct labor
Q76: Unfavorable standard cost variances are normally closed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents