We Identify the Critical Path of a Project as

Question 38

Multiple Choice

We identify the critical path of a project as


A) any path that goes from the starting node to the completion node.
B) the combined time of all paths of the project.
C) the shortest path through the project.
D) the longest path through the project.

Correct Answer:

verifed

Verified