If the total projected error in an account balance was $3,248 and the tolerable error was set at $10,000, the auditor would:
A) conclude that the errors uncovered are material.
B) decide that further audit work was required.
C) conclude that the errors detected are not material.
D) conduct other tests aimed at the assertion being tested.
Correct Answer:
Verified
Q27: What impact will there be on sample
Q35: When testing controls, the tolerable error is
A)
Q36: What impact will there be on sample
Q38: Which of the following statements is incorrect?
A)
Q41: An account is at a higher risk
Q46: Indicate whether you agree or disagree with
Q53: Explain how auditors evaluate the results of
Q56: When evaluating sample test results, which of
Q57: Explain sampling risk as it relates to
Q59: Identify and explain the factors that influence
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents