Question 17

Multiple Choice

A static budget:


A) should be compared to actual costs to assess how well costs were controlled.
B) should be compared to a flexible budget to assess how well costs were controlled.
C) is valid for only one level of activity.
D) represents the best way to set spending targets for managers.