Rubyor Corporation bases its predetermined overhead rate on variable manufacturing overhead cost of $10.70 per machine-hour and fixed manufacturing overhead cost of $821,104 per period.If the denominator level of activity is 7,300 machine-hours,the variable element in the predetermined overhead rate would be:
A) $112.48
B) $123.18
C) $121.66
D) $10.70
Correct Answer:
Verified
Q26: Franklin Glass Works uses a standard cost
Q27: Temores Corporation applies manufacturing overhead to products
Q28: Franklin Glass Works uses a standard cost
Q29: Coskey Corporation applies manufacturing overhead to products
Q30: Morisey Corporation bases its predetermined overhead rate
Q32: Sommers Fabrication Corporation has a standard cost
Q33: Jay Company uses a standard cost system
Q34: Heroman Corporation applies manufacturing overhead to products
Q35: Franklin Glass Works uses a standard cost
Q36: Trecroci Corporation applies manufacturing overhead to products
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents