When the actual amount of a raw material used in production is greater than the standard amount allowed for the actual output, the journal entry would include:
A) Credit to Raw Materials; Credit to Materials Quantity Variance
B) Credit to Work-In-Process; Credit to Materials Quantity Variance
C) Credit to Raw Materials; Debit to Materials Quantity Variance
D) Credit to Work-In-Process; Debit to Materials Quantity Variance
Correct Answer:
Verified
Q11: If the actual rate per direct labor-hour
Q12: If the actual direct labor-hours used is
Q13: If the actual rate per direct labor-hour
Q14: During the month of May, Marian Manufacturing
Q15: When the actual wage rate paid to
Q17: A favorable labor efficiency variance is recorded
Q18: An unfavorable materials price variance is recorded
Q19: If the actual quantity of materials used
Q20: A favorable labor efficiency variance would result
Q21: Slife Corporation has provided the following data
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents