Planning must be done before performing any function. A schedule is a time-phased plan. The principal uses of schedules in the implementation process are outlined in the textbook. The list below contains items from the section entitled, Before Starting Project. One does not belong. Which one is incorrect?
A) Forms the basis for management to issue instructions to subordinates.
B) Establishes the planned rate of progress.
C) Identifies the expenses associated with the use of manpower, materials, and machines.
D) Establishes the planned sequence for the use of manpower, materials, machines, and money.
E) Provides an estimate of the time required for each portion of the project as well as for the total project.
Correct Answer:
Verified
Q17: Some factors that may contribute to a
Q18: The need for _ in all types
Q19: _ include materials, labor, and subcontract expenditures
Q20: In order to be successful, the project
Q21: Planning must be done before performing any
Q23: ecause of its impact on the entire
Q24: _ is described as follows: CPM is
Q25: _ is described as follows: Once the
Q26: The _ is a robust logical system
Q27: One of the tasks involved in a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents