Mansfield Corporation estimates its manufacturing overhead costs to be $160,000 and its direct labor costs to be $320,000 for 2012.The actual manufacturing labor costs were $80,000 for job 1,$120,000 for job 2 and $160,000 for job 3 during 2012.Manufacturing overhead is applied to jobs on the basis of direct labor costs using a predetermined overhead rate.The actual manufacturing overhead cost for the year was $172,000.The amount of overhead assigned to Job 3 during 2012 was:
A) $80,000.
B) $320,000.
C) $160,000.
D) $71,110.
Correct Answer:
Verified
Q15: Which of the following is the correct
Q16: Which of the following would probably be
Q67: The predetermined manufacturing overhead rate for the
Q77: The predetermined manufacturing overhead rate for the