Ollivier Corporation has an activity-based costing system with three activity cost pools-Processing, Supervising, and Other. In the first stage allocations, costs in the two overhead accounts, equipment expense and indirect labor, are allocated to the three activity cost pools based on resource consumption. Data used in the first stage allocations follow:
Processing costs are assigned to products using machine-hours (MHs) and Supervising costs are assigned to products using the number of batches. The costs in the Other activity cost pool are not assigned to products. Activity data for the company's two products follow:
-What is the overhead cost assigned to Product L7 under activity-based costing?
A) $1,672
B) $9,022
C) $7,350
D) $19,000
Correct Answer:
Verified
Q88: Groch Corporation uses activity-based costing to compute
Q89: Umanzor Corporation uses activity-based costing to assign
Q90: Brisky Corporation uses activity-based costing to compute
Q91: Groch Corporation uses activity-based costing to compute
Q92: Umanzor Corporation uses activity-based costing to assign
Q94: Dykema Corporation uses activity-based costing to compute
Q95: Ballweg Corporation has an activity-based costing system
Q96: Brisky Corporation uses activity-based costing to compute
Q97: Ballweg Corporation has an activity-based costing system
Q98: Laningham Corporation uses an activity based costing
Unlock this Answer For Free Now!