Hart Manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 45% of the total throughput (manufacturing cycle) time is spent on non-value-added activities. Delivery cycle time is 12 hours, waiting time during the production process is 3 hours, queue time prior to starting the production process is 2 hours, and inspection time is 1.2 hours.
-What is the throughput (manufacturing cycle) time for the operation?
A) 12.0 hours
B) 9.0 hours
C) 10.0 hours
D) 5.8 hours
Correct Answer:
Verified
Q75: Chace Products is a division of a
Q76: The following data pertain to the Whalen
Q77: Dickonson Products is a division of a
Q78: The following data pertain to the Whalen
Q79: Chace Products is a division of a
Q81: Gilde Industries is a division of a
Q82: Eckels Wares is a division of a
Q83: Saffer Corporation keeps careful track of the
Q84: Heavey Fabrication is a division of a
Q85: Waltner Corporation's management reports that its average
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents