Hart Manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 45% of the total throughput (manufacturing cycle) time is spent on non-value-added activities. Delivery cycle time is 12 hours, waiting time during the production process is 3 hours, queue time prior to starting the production process is 2 hours, and inspection time is 1.2 hours.
-The manufacturing cycle efficiency (MCE) for this operation is:
A) 55%
B) 45%
C) 6.6 hours
D) 5.4 hours
Correct Answer:
Verified
Q63: Chace Products is a division of a
Q64: Chace Products is a division of a
Q65: The following data pertain to the Whalen
Q66: Chace Products is a division of a
Q67: Saffer Corporation keeps careful track of the
Q69: Saffer Corporation keeps careful track of the
Q70: Hart Manufacturing operates an automated steel fabrication
Q71: Dickonson Products is a division of a
Q72: Dickonson Products is a division of a
Q73: Dickonson Products is a division of a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents