Verification of all project deliverables occurs during ___.
A) Conceptualize and initialize the project Phase 1)
B) Develop the project charter and plan Phase 2)
C) Execute and control Phase 3)
D) Close project Phase 4)
E) Evaluate project success Phase 5)
Correct Answer: