The budgeted cost of work scheduled for an activity or component of the WBS is the _____.
A) Planned Value (PV)
B) Budget At Completion (BAC)
C) Actual Cost (AC)
D) Expected Time Complete (ETC)
E) Estimate at Completion (EAC)
Correct Answer:
Verified
Q27: The metric that provides an estimate of
Q28: The total planned cost of the project
Q29: Budget At Completion (BAC) is _
A) how
Q30: EV-AC =
A) Cost performance index (CPI)
B) Scheduled
Q31: If you hired a consulting firm to
Q33: Cost Variance (CV) is _
A) how much
Q34: Earned Value tells us _
A) how much
Q35: Expected Time to Completion (ETC) is _
A)
Q36: Barring a change in project scope and
Q37: A metric that provides an estimate for