A work element in the project plan requires 50 hours of labor each by four carpenters.The carpenters are paid $15 per hour and incur an overhead rate equal to 80 percent of their direct labor charges.Based on this data,the appropriate total cost is __________.
A) $2,400
B) $3,000
C) $5,400
D) $4,600
Correct Answer:
Verified
Q10: The _ form of budgeting has the
Q13: The project's budget should _.
A)associate resource use
Q17: The _ charge is composed of the
Q19: _ are where the defined responses to
Q23: The budget process generally begins when the
Q23: A work element in the project plan
Q24: Suppose that a person requires eight hours
Q26: Suppose that a person requires 60 minutes
Q41: _ budgeting aggregates income and expenditures by
Q52: Describe the top-down budgeting process.