Using Goldratt's Meaning of the Word "Dependent," the Activities of a Project
Question 41
Multiple Choice
Using Goldratt's meaning of the word "dependent," the activities of a project can be ordered into paths based on their resource dependencies as well as on their technological precedence requirements.The longest of these paths of sequentially time-dependent activities is known as the ______________.
A)priority chain
B)critical chain
C)dependency path
D)heuristic path