Which of the following statements is NOT true about project duration as an external attribute that contributes to project complexity?
A) The duration of a project is often set by the parent organization that charters the project.
B) The project deadline reflects the business purpose of the project.
C) The project team estimates the duration of the project.
D) The project team establishes a project end date based on normal work.
E) The normal time needed to complete a project is always longer than the time available.
Correct Answer:
Verified
Q44: Which of the following statements is true
Q45: Goal-based cultures:
A) inhibit risk taking through established
Q46: Which of the following statements is true
Q47: _ is a term that reflects the
Q48: Institutions of higher learning and most government
Q50: _, the more stress that is placed
Q51: The DPCI was developed around four assumptions.
Q52: According to the Darnall-Preston Complexity Index DPCI),
Q53: _, the greater the stress and the
Q54: In terms of stakeholder agreement, which of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents