Which of the following statements is true regarding the Darnall-Preston Complexity Index DPCI) ?
A) The DPCI groups ten project attributes into four broad categories.
B) The categories of the DPCI are internal attributes, external attributes, technological complexity, and system scope.
C) The DPCI helps in defining the experience, knowledge, skills, and abilities needed by the project manager.
D) The DPCI has the tendency to further complicate the process of developing a project execution plan.
E) The DPCI has little impact on the composition and organization of the project leadership team.
Correct Answer:
Verified
Q26: Which among the following is an example
Q27: Which of the following were the two
Q28: The ecology includes the sights and sounds
Q29: _ is the process of extracting a
Q30: In addition to the number of parts,
Q32: _ identified differences in project types based
Q33: An) _ is defined as an organization
Q34: Which of the following statements is true
Q35: Research by the Construction Industry Institute indicated
Q36: A _ is a method of incorporating
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents