If the money needed to pay for a project is transferred to the project too far in advance:


A) the process of reconciliation becomes easier.
B) there will be a delay in the start of the project or the activity.
C) the organization will lose the opportunity to use the money somewhere else.
D) the organization will end up paying lesser interest charges if the money is borrowed.
E) the organization will have access to funds as and when they are needed.