The project manager should involve every project member in developing the WBS to have special expertise, knowledge, or experience that will help develop a more comprehensive and complete WBS.
Correct Answer:
Verified
Q26: The project quality plan should state which
Q27: The work breakdown structure subdivides the project
Q28: The quality plan may also state that
Q29: With the quality plan in place including
Q30: The work package includes all of the
Q32: The customer may randomly select certain work
Q33: It is essential to wait until the
Q34: The WBS usually indicates the organization or
Q35: The network diagram can be created using
Q36: The key to quality control is to