The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows: What is the amount of the factory overhead volume variance?
A) $12,000 unfavorable
B) $12,000 favorable
C) $14,000 unfavorable
D) $26,000 unfavorable
Correct Answer:
Verified
Q96: The following data relate to direct labor
Q97: The standard costs and actual costs for
Q98: Which of the following is not a
Q99: The following data relate to direct labor
Q100: The formula to compute direct labor time
Q102: Assuming that the standard fixed overhead rate
Q103: The St. Augustine Corporation originally budgeted for
Q104: The standard costs and actual costs for
Q106: The following data is given for the
Q120: Incurring actual indirect factory wages in excess
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents