Solved

Just-In-Time Manufacturing
Candycane Co (A) Which of the Above Activities Are Value-Added Activities?
(B)

Question 64

Essay

Just-in-time manufacturing
Candycane Co. is trying to determine how long it takes for one of its products to pass through the production process. The following information was assembled regarding how many days the product spends in various production activities:
 Activity  Number of days  Inspection 12 Storage 14 Assembly 8 Handling 6 Painting 8 Packaging 4\begin{array} { | l | c | } \hline \text { Activity } & \text { Number of days } \\\hline \text { Inspection } & 12 \\\hline \text { Storage } & 14 \\\hline \text { Assembly } & 8 \\\hline \text { Handling } & 6 \\\hline \text { Painting } & 8 \\\hline \text { Packaging } & 4 \\\hline\end{array}
(a) Which of the above activities are value-added activities?
(b) What is Candycane's total cycle time?
(c) Determine Candycane's manufacturing efficiency ratio.

Correct Answer:

verifed

Verified

(a) Value added activities include: Asse...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents