Answer Corporation Uses Standard Cost System Variable Cost @ $2 Per Hour
Total Variable Cost, $18,000
Answer Corporation uses standard cost system. The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows:
Variable cost @ $2 per hour
Total variable cost, $18,000
Fixed cost @ $0.80 per hour
Total fixed cost, $8,000
Refer to the information provided for Answer Corporation. The amount of the direct labor rate variance is:
A) $4,440 unfavorable.
B) $4,500 favorable.
C) $4,440 favorable.
D) $4,500 unfavorable.
Correct Answer:
Verified
Q126: The following data relate to direct
Q127: Answer Corporation uses standard cost system.
Q127: If the wage rate paid per hour
Q128: The standard costs and actual costs
Q131: The formula to compute direct material quantity
Q131: The following data relate to direct
Q132: Frogue Corporation uses a standard cost
Q133: The following data relate to direct
Q134: The following data relate to direct
Q135: The standard costs and actual costs
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents