For Long-Term Construction Contracts, When There Is Not Assurance That

Question 33

Multiple Choice

For long-term construction contracts, when there is not assurance that the buyer can be expected to satisfy its obligations under a contract, which of the following revenue recognition methods is preferable?


A) percentage-of-completion method
B) installment method
C) deferral method
D) completed-contract method