Which of the following is a major weakness of the engineering method of cost estimation?
A) The method is not particularly useful when the physical relation between inputs and outputs is indirect.
B) The method is subjective.
C) The method requires that several relatively strict assumptions be satisfied.
D) The method is based on studies of what future costs should be rather than what past costs have been.
Correct Answer:
Verified
Q65: One of the weaknesses of the various
Q66: The method of cost estimation which studies
Q67: Which of the following is a weakness
Q68: Which of the following can complicate the
Q69: Which of the following is a statistical
Q71: What are selling,general and administrative costs considered
Q72: Analysts should take which step(s)in analyzing cost
Q73: Which of the following is a strength
Q74: If all the data points were on
Q75: The method of cost estimation where the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents