For projects whose activities have probabilistic time estimates, the probability of completing the project in a specified amount of time is determined by __________________________.
A) the expected time for the critical path only
B) the standard deviation for the critical path only
C) the expected time and standard deviation for the critical path only
D) the expected times for all paths
E) the expected times and standard deviations for the critical path and paths whose expected times are close to that of the critical path
Correct Answer:
Verified
Q41: There are four activities on the critical
Q42: What can be used to display graphically
Q43: You may be able to speed up
Q44: In monitoring the progress of a project,
Q45: The probability of completing a project in
Q47: Crashing a schedule is reducing a project
Q48: An activity in a network diagram has
Q49: Which of the following information about activities
Q50: Joe's tower fabrication company client would like
Q51: Which of the following is not a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents