Which of the following is not a direct input to capacity requirements planning?
A) planned shop orders
B) open shop orders
C) setup time and run time per unit for shop orders
D) current inventory levels
E) quantity for shop orders
Correct Answer:
Verified
Q71: Different lot size rules determine the quantity
Q72: Supply chain intelligence enables strategic decision-making along
Q73: If setup costs are essentially zero (negligible
Q74: Capacity requirements planning enables the company to
Q75: ERP systems are more commonly found in
Q77: Which of the following does not share
Q78: Capacity requirements planning uses data from _.
A)
Q79: If the available capacity at a work
Q80: Dell practices _.
A) focused customization
B) make to
Q81: Production and inventory planners release orders to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents